Kolb Grading was awarded a contract to grade the pump-station site in Salisbury, Missouri. The scope included topsoil stripping, scarifying and re-compacting, over 4,500 cubic yards of on-site cut, more than 2,000 linear feet of ditches and berms, 30,000 square feet of 60-mil HDPE liner, 6- to 12-inch CSP pipe, and rip-rap placement in ditches.
Scope of Work
- Strip topsoil; scarify and re-compact
- Over 4,500 cy of on-site cut
- Over 2,000 lf of ditches and berms constructed
- 30,000 sf of HDPE 60-mil liner installation
- Survey and layout; file preparation
- 6” to 12” CSP pipe installation
- Rip rap hauled in and placed in ditches